The red area is an approximate outline of the slip area.

 This area is far above the newer building below.

 

 

The reader will eventually understand how important the 2005 Agreement to correct the area was, not only for us, but for the developer, other businesses, the city, public infrastructure and this complete, as advertised thirty million dollar development.

 

   

 

The blue line area is the toe area referred to in the Terradon report. The slip is not in this area. It is above, where the red barn resides. (Irrefutable evidence is later shown under the heading road construction).

 

The wooded area has the same natural slope and build as the area between the barn and new building. There was no "digging" out of this area.

 

Furthermore; A dense locust root system existed between the new building and red barn. As such, locust trees sprouted immediately and very aggressively.

 

 

 

If there had been a "digging out" of the area the root structures would have been dug out in the process.

The result would have been erosion, similar to what is shown in this picture, which is opposite in design, as well as location.

 
 
 
As stated, locust trees sprouted immediately. (Fall picture, as such the large amount of locust trees is not as apparent as they are in the summer).

The locust trees were even pruned to create a bush like growth. The pruning was advised by Frank Lacaria, who has lived in this area for 85 years. As one contractor stated that he knows this land so well it is as though it is alive to him. This is a older engineering principle, lost to many engineers under the age of 65.

For perspective; Another observation of Frank Lacaria, that is eerily uncanny, is mentioned here.

 




The above information provides insight however it is unnecessary because of the following information:

One of the most respected and experienced contractors performed our site preparation. This surprised some, as this developer only worked on commercial developments.

A larger number of tandem trucks over multiple days delivered compactable fill from other developments in the Bridgeport area.

The compacted area was brought to absolute level by the use of electronic surveying laser. A bull dozer with a large vibrating roller compacted the fill at every 2 feet in height as the area was raised to it's finished level.

After the fill compaction, tons of gravel was then compacted over the fill surface, before seventy five yard of concrete was placed for a 8 inch concrete floor.

The delivery of fill, along with the subsequent compaction work alone had cost in the neighborhood of fifteen thousand dollars, (15,000.00). This of course widened the building area, and in the process strengthened the toe area of the hill. Though some may consider it overboard, one city official noted that it obviously strengthened the area.

For more of a perspective, jump ahead to the titled Repair Diagram.